Way behind schedule, Meeker Slough cleanup is expected to begin later this year
on November 6, 2026
In Richmond’s Marina Bay neighborhood, cyclists pass along the Bay Trail as squirrels forage for nuts and ducks rest nearby. Just steps away, the receding tide at Meeker Slough reveals an abandoned shopping cart, car seat and a chair. An oil barrel sits idly in the water, covered with moss.

“I think some of those things have been there the whole time,” said Marcia Gibbs, a resident who has lived in Marina Bay for 20 years. “I’m amazed that they’re still there. But I’ve never seen any attempt to get them out.”
In fact, the city has been working on the cleanup for more than a year. It now expects to begin by the end of 2026, more than a year after the project’s original September 2025 start date.
Why has it taken so long to clean such a short and narrow mudflat channel?
Local governments must notify the California Department of Fish and Wildlife before undertaking activities that may substantially alter the natural flow, bed, channel or bank of a river, stream or lake. Tawfic Halaby, Richmond’s deputy director of public works, said the city submitted a detailed work plan for streambed alteration.
“It gets more complicated because it’s a sensitive habitat,” Halaby said. “And more complicated because there are species that are protected.”

Meeker Slough, southeast of Marina Bay, isn’t only a place for residents to enjoy outdoor recreation but also a key habitat for wildlife, including the federally endangered Ridgway’s rail. However, it is littered with debris.
Land surrounding Meeker Slough has been used for manufacturing and industrial activities since the late 1800s, and contaminants were later found in nearby wetlands, according to the Golden Gate Bird Alliance.
According to the streambed alteration agreement between Richmond and the Fish and Wildlife, some of the debris will be removed manually from small boats in the environmentally sensitive area. The work could disturb wetland birds and stir up sediment, releasing contaminants and harming wildlife, Fish and Wildlife cautions.

The protections are standard, said Jen McBroom, the senior biologist who has monitored the Ridgway’s rail population with Olofson Environmental Inc. for the past decade. McBroom said the cleanup could have a temporary impact on the birds, but she did not expect it to affect them overall.
To protect wildlife during cleanup, the scope of work was expanded to increase work days and adding precautionary measures, such as contractor training and having a biologist on site. The agreement also warns that unauthorized harm to state or federally protected species could result in prosecution and nullification of the agreement.
According to McBroom, surveys at Meeker Slough have recorded around 10 Ridgway’s rails annually in recent years, suggesting a relatively stable number. The 2025 survey recorded 17 rails, the highest count in recent years, compared with two in 2010.

McBroom said removing the debris would benefit the habitat by allowing plants to grow in its place. “If there is a couch or sofa there, plants can’t grow there, and I think plants are better for the habitat,” she said.
She agreed with the clean-up plan and expressed support for the precautionary measures listed in the agreement. McBroom is more concerned about the potential impact of the coming El Niño and winter king tides than about the cleanup itself.
“Birds don’t have many places to hide when the tide is high,” she said.
After the initial cleanup, which is expected to take one to two days, Richmond plans to clean up Meeker Slough twice a year.
The city still needs to obtain the permit and hire a contractor. The work must be scheduled for suitable tidal and weather conditions, and must happen before Jan. 15 to avoid the Ridgway’s rail breeding season.
Scooter collision in El Cerrito highlights need for Ohlone Greenway improvements
Richmond Confidential welcomes comments from our readers, but we ask users to keep all discussion civil and on-topic. Comments post automatically without review from our staff, but we reserve the right to delete material that is libelous, a personal attack, or spam. We request that commenters consistently use the same login name. Comments from the same user posted under multiple aliases may be deleted. Richmond Confidential assumes no liability for comments posted to the site and no endorsement is implied; commenters are solely responsible for their own content.